Method of statement for mechanical works pdf

Below is the list of mechanical HVAC method statements which you can download as per your requirements. This method statement covers on site installation of pre-fabricated and site fabricated mild steel pipework including supports, expansion and anchor points for chilled water system. This procedure is to define the method used to ensure that the Chilled Water Pipework System installation is as per project requirements.

Method of statement for mechanical works pdf

There are certain erection practices which are in general use and have proven sound over the years. Flame cleaning is another method of surface cleaning. In this method the surface is cleaned using an oxy-acetylene torch which works on the principle of differential thermal expansion between steel and mill scale.

In another method called the ‘ steel piece is immersed in a suitable acid and the scale and rust are removed. INTRODUCTION AND PURPOSE 1. This specification covers the installation, testing and pre-commissioning of mechanical equipment. Contact customer‟s management to gain permission and to advise of work to be carried out. Where require complete Hot Work Permit and adhere to any rules printed thereon, over and above these procedures.

A fire extinguisher of the correct type must be present and within. The foreman will carry out a risk assessment before carrying out work at height and put in place equipment and measures to prevent falls occurring. This statement of work (SOW) describes the technical requirements of a maintenance and repair contract for electricity power generators (no.), sizes and makes are different as per the below table which contains information on the technical data of these generators. Fixing Conduits and GI boxes in the columns. Before casting any column in the site, we have to check if there is any Switch Socket, bell or break glass fixed on the column.

Method Statement free download. Machinery and Equipment 5. Personal Protective Equipment 5. Safety Arrangement during the foundation work 6. Survey and Setting out 6. Piles (where applicable) 6. To ensure that the works are carried out according to the Contract Specifications, approved method statement and the shop drawings. To provide all necessary information and distribute responsibilities to his construction team. To monitor the progress of work in relation with the work program and to report to the Project Manager. PCBUs can use this as a general example, but would need to adapt this to be workplace specific.

Method of statement for mechanical works pdf

During the proposed works the existing heat exchangers are planned to be removed from site and the existing buffer vessels require modifications. Installation of Outfall Extension. A method statement for various hvac installation works. An icon used to represent a menu that can be toggled by interacting with this icon. Plant and equipment utilised (tick or add as applicable) – Attach evidence to this SWMS Item (including all mechanical and electrical items) List inspections and maintenance requirements and attach evidence to this SWMS Note: All servicing MUST be in accordance with manufacturers recommendations.

Vehicles fitted with reversing alarms. Adequate compound lighting vi. Soft surfaces lay hard-core or other temporary surfacing. Horizontal Directional Drilling (HDD) is a trenchless method used during pipeline installation that is effective at minimizing disturbance on the surrounding environment. The traditional method of pipeline installation under watercourses is termed isolated open-cut, where surface and subsurface disturbance is created during pipeline construction.

All the above works are described in detail within the later sections of this specification along with the Mechanical and Electrical tender drawings. Scope of Work : Engineered Wood Flooring This form serves as a guide only. AL REYAMI ELECTROMECHANICAL.

UNDER GROUND DRAINAGE PIPE WORK 1. Purpose To define the method of installation of underground pipe work. Scope This method is applicable for drainage pipe work below ground. Preparation 1) Report to site office and inform site manager of arrival, collect permit to work where required.

Method of statement for mechanical works pdf

STATEMENT OF WORK Proposal No.

Leave a Reply

Your email address will not be published. Required fields are marked *