Contract variation process

What is contract variation? Contract variations should be agree in writing and signed by both parties. In the process of handling variations, you will find few steps as mentioned below. Therefore variations play a big impact on cost management of any construction project. At the same time, consultants like to deliver their projects within the stipulated budget.

Therefore they look every ways that they can save money avoiding cost overruns. Sometimes, these variation instructions end up as disputes to the contract. See full list on sihelaconsultants.

There are many causes for variations in construction projects. Below are some of the reasons for variations. However for specific projects, you should refer the contract document to find specific terms and clauses that are relevant to your project. Addition or omission from the scope of works 1. Variations can be due to, 1. Removal of part of the scope or demolition of part of the work scope by the Employer which affects the total scope of work. Changes to the construction quality including material quality changes.

Contract variation process

Due to changes in the schedule of completion. As a result, variations to the contract may occur. Simply, variation to the contract means any chan. I have experience that most of the time the terms variation order or VO are more popular to introduce any variations to the contract.

However variations to the contract are the changes to the contract as we discussed at the beginning of this post. Only the authority person to the contract can issue such instructions. A variation to be vali it must be in writing. Such instructions issued by the authority person are known as a variation order to the project. The authority person can be architect, superintending officer or contract administrator who has the power to issue instructions.

Contract variation process

In your contract agreement you can find a clause that mentions the authority person. If the contractor receives verbal instructions to carry out some extra work in the way of addition or omission, he should write it to the Architect or superintending officer to get approval in order to make it a valid variation order. When there is a variation and it is instructed as a written instruction, the contractor is required to submit his proposal for the consultants or client for evaluation.

Once the variation claim is submitte then valuation is done by the consultant Quantity Surveyor or the responsible cost consultant. Valuation of variations plays an important role in variation claim procedure. At this stage, it also can be a dispute for the contract. However, if the contractor understands the procedure of variation claim preparation and submission and if he also understands the provisions for variation claims in his contract agreement, variation claim procedure is not much difficult. However, it is necessary to refer your contract agreement and relate.

After the work is complete he needs to submit his variation claim at the time when he submits the progress claim. Together with his claim, it is necessary to submit the necessary documents and details to support his claim. There may have situations which contractor receives instructions to carry out the work under daywork. In such times, contractor should inform the Contract administrator, superintendent officer or the respective clients representative of the time the work being carried out.

It is necessary for the contractor to keep signed day work records in order to submit with his claim. In general, this is how to conduct valuation of variations. Also it is contractor’s responsibility to submit his variation claim with all necessary details in order to get the payment certified within a reasonable time period. Almost all construction projects vary from the original design, scope and definition. These conditions and method.

Whether small or large, construction projects will inevitably depart from the original tender design, specifications and drawings prepared by the design team. The valuation of variations may include not just the work which the variation instruction describes, but other expenses that may result from the variation , such as the impact on other aspects of the works. Agreement between the contractor and the client. Conflict can arise when work is not mentioned in the bills of quantities, drawings or specifications. In common law this silence does not mean the contractor has an automatic right to claim for extra payment.

The client is not bound to pay for things that a reasonable contractor must have understood were to be done but which happen to be omitted from the bills of quantities. Where there are items that, whilst they are not expressly mentione are nonetheless required in order to complete the w. Whilst some variations are unavoidable, it is wise to minimise potential variations and subsequent claims by ensuring that uncertainties are eliminated before awarding the contract. Undertaking thorough site investigations and condition surveys. Extension of time EOT in construction contracts 2. Architect’s instruction 3. This can be done by: 1. Campaign for cash retentions reform.

Contract variation process

Alterations to existing buildings 6. Change order for construction contracts 5. Liquidated damages in construction contracts 8. Construction contract 9. Abortive work in building design and construction 12. Compensation event 11. Payment for extra work 13. Bill of quantities BOQ 14.

The JCT Standard Building Contract : Law and Administration By Issaka Ndekugri, Michael Rycroft. Many times clients visit site during the course of construction and request a different material or a structural change to the building plans. Such changes may be necessary as a result of a change in circumstances that could not be anticipated or quantified when the PPP agreement was signed.

It is an act of changing certain specifications from the final plan on the construction contract. Changes are inevitable, especially in conceiving a project. The latter is the one that most of us will think of when the term variation is used.

A contract can, however, be varied by an oral agreement or by its parties’ conduct, even where the contract itself contains a “no oral variation ” clause. User Division may also initiate a variation request based on the changing needs of the project. All entities varied contracts during the period of our audit. Their records showed total variations of.

If the Contract Manager concludes that it is not feasible or suitable to proceed with the proposed Contract , the Contract Manager must advise the Other Party without delay.